Hyway Hyway
Hyway Hyway
Production order PO-26-0400 Demo 2 × 175/360 · Complete
Xero connected · synced 9:14am 19 Aug 2026
← The floor Complete
Pairs
2/2
none scrapped
Hours
7.8
against 7.9h estimated
Material issued
$2,946
of $2,946 planned
Scrap off the saw
3.41kg
3 cut plans run
Off the remnant rack
5.7m
metal not bought new
Routing
Standard minutes against booked, work centre by work centre.
SeqWork centreWhat happensWhoStatusStdBookedVariance
1 CUT Cutting — 4 rails at 3600mm, 26 rungs at 474mm Harinder Singh Done 70 min 73 +4%
2 DRILL Drilling — Rail jig, headplate and pin holes Harinder Singh Done 46 min 50 +9%
3 WELD Welding — 52 rung joins, 2 headplates Nelson De Villa Done 172 min 182 +6%
4 ASSY Assembly — Nose, lugs, pins, ID plate Harinder Singh Done 62 min 67 +8%
5 INSP Inspection — Proof load and dimensional check Oliver Brewer Done 70 min 65 -7%
6 PACK Packing — Bearers, strap, wrap, label Nick Kennedy Done 56 min 55 -2%
Cutting and nesting
What has to be cut to length, and how it was nested onto bar and remnant.
ProfilePiecesCut toTotal lengthCut planYieldOff the rack
EXT-175-SR
175 Series side rail extrusion
8 3,600mm 28.80m CP-26-0321 99.0% 0 · 0.0m
EXT-NOSE
Nose / toe extrusion
4 450mm 1.80m CP-26-0323 98.9% 1 · 1.8m
EXT-RUNG-HD
Heavy duty rung — Hyway profile
52 474mm 24.65m CP-26-0322 96.1% 1 · 3.8m
Material
Required against issued, priced at what the buyer last paid.
2 short
CodeMaterialBinRequiredIssuedOn handCost
GAS-ARG Argon E-size cylinder RM-E1 0.189 ea 0.189 9.42 $18.16
WIRE-5356 5356 MIG wire 1.2mm, 7kg spool RM-E1 0.095 spool 0.095 20.76 $11.16
EXT-175-SR 175 Series side rail extrusion
8 at 3600mm
RM-A1 28.800 m 28.800 -61.10 $1,599.84
EXT-NOSE Nose / toe extrusion
4 at 450mm
RM-B1 1.800 m 1.800 279.80 $35.01
EXT-RUNG-HD Heavy duty rung — Hyway profile
52 at 474mm
RM-B1 24.648 m 24.648 -119.30 $637.15
PLATE-ID Serial identification plate RM-D1 4.000 ea 4.000 434.26 $16.80
RIVET-4 4mm rivet, stainless, pack of 500 RM-D1 0.016 pack 0.016 12.05 $1.18
STRAP-PP 19mm poly strapping, 1000m coil RM-E1 0.024 coil 0.024 5.80 $2.06
TIMB-BEAR Timber bearer 100×50, 1.2m RM-E1 4.000 ea 4.000 247.68 $29.60
WRAP-PAL Pallet wrap 500mm × 400m RM-E1 0.100 roll 0.100 20.67 $2.15
PIN-14-S 14mm steel pin, zinc plated RM-D1 8.000 ea 8.000 423.19 $92.80
PIN-CHAIN Pin retaining chain, 300mm RM-D1 8.000 ea 8.000 725.03 $31.20
PL-GUSS-6 6mm gusset plate 1200×600 RM-C1 0.200 sheet 0.200 13.40 $30.40
PL-HP-10 10mm headplate plate 2500×1250 RM-C1 0.400 sheet 0.400 2.05 $438.00
Planned material$2,945.51
Labour booked
8.2 hours off the floor against this order.
DateWhoWork centreMinutesDoneScrapNote
19 Aug Nick Kennedy PACK 55 2
19 Aug Harinder Singh ASSY 67 2
19 Aug Nelson De Villa WELD 182 2
19 Aug Harinder Singh DRILL 50 2
18 Aug Oliver Brewer INSP 65 2
18 Aug Harinder Singh CUT 73 2
Ramps built
One serial per ramp, with the batch it came from and who signed it off.
SerialBuiltCapacityLengthBatchWelderInspectedStatus
HY-26-41192 24 Jun 6,000kg 3.6m VUA-24578 Dion Field Oliver Brewer In service
HY-26-41193 2 Jul 6,000kg 3.6m VUA-24959 Nelson De Villa Oliver Brewer In service
HY-26-41194 14 Aug 6,000kg 3.6m VUA-24548 Dion Field Oliver Brewer In service
HY-26-41195 24 Jul 6,000kg 3.6m VUA-24774 Dion Field Oliver Brewer In service