Hyway Hyway
Hyway Hyway
Production order PO-26-0441 Demo 1 × L75 300 · Packing
Xero connected · synced 9:14am 19 Aug 2026
← The floor Packing
Pairs
1/1
none scrapped
Hours
3.2
against 3.1h estimated
Material issued
$533
of $533 planned
Scrap off the saw
0.00kg
0 cut plans run
Off the remnant rack
0.0m
metal not bought new
Routing
Standard minutes against booked, work centre by work centre.
SeqWork centreWhat happensWhoStatusStdBookedVariance
1 CUT Cutting — 4 rails at 3000mm, 18 rungs at 374mm Harinder Singh Done 30 min 31 +3%
2 DRILL Drilling — Rail jig, headplate and pin holes Harinder Singh Done 19 min 20 +5%
3 WELD Welding — 36 rung joins, 2 headplates Dion Field Done 60 min 54 -10%
4 ASSY Assembly — Nose, lugs, pins, ID plate Harinder Singh Done 25 min 22 -12%
5 INSP Inspection — Dimensional check and weld inspection Oliver Brewer Done 32 min 32 +0%
6 PACK Packing — Bearers, strap, wrap, label Nick Kennedy Running 22 min 14 -36%
Cutting and nesting
What has to be cut to length, and how it was nested onto bar and remnant.
ProfilePiecesCut toTotal lengthCut planYieldOff the rack
EXT-L75-SR
L75 side rail extrusion
4 3,000mm 12.00m Not run
EXT-NOSE
Nose / toe extrusion
2 350mm 0.70m Not run
EXT-RUNG-LT
Light rung — Hyway profile
18 374mm 6.73m Not run
Running the plan looks at what is on the remnant rack before it opens a new mill length, takes the shortest piece that will do the job, and puts anything over 600mm back on the rack as a new remnant.
Material
Required against issued, priced at what the buyer last paid.
CodeMaterialBinRequiredIssuedOn handCost
GAS-ARG Argon E-size cylinder RM-E1 0.077 ea 0.077 9.42 $7.42
WIRE-5356 5356 MIG wire 1.2mm, 7kg spool RM-E1 0.039 spool 0.039 20.76 $4.55
EXT-L75-SR L75 side rail extrusion
4 at 3000mm
RM-A3 12.000 m 12.000 460.10 $275.40
EXT-NOSE Nose / toe extrusion
2 at 350mm
RM-B1 0.700 m 0.700 279.80 $13.62
EXT-RUNG-LT Light rung — Hyway profile
18 at 374mm
RM-B1 6.732 m 6.732 547.70 $119.16
PLATE-ID Serial identification plate RM-D1 2.000 ea 2.000 434.26 $8.40
RIVET-4 4mm rivet, stainless, pack of 500 RM-D1 0.008 pack 0.008 12.05 $0.59
STRAP-PP 19mm poly strapping, 1000m coil RM-E1 0.012 coil 0.012 5.80 $1.03
TIMB-BEAR Timber bearer 100×50, 1.2m RM-E1 2.000 ea 2.000 247.68 $14.80
WRAP-PAL Pallet wrap 500mm × 400m RM-E1 0.050 roll 0.050 20.67 $1.08
PIN-10-S 10mm steel pin, zinc plated RM-D1 2.000 ea 2.000 443.47 $16.80
PIN-CHAIN Pin retaining chain, 300mm RM-D1 2.000 ea 2.000 725.03 $7.80
PL-HP-6 6mm headplate plate 2500×1250 RM-C1 0.095 sheet 0.095 20.23 $62.55
Planned material$533.20
Labour booked
2.9 hours off the floor against this order.
DateWhoWork centreMinutesDoneScrapNote
19 Aug Harinder Singh CUT 31 1
18 Aug Nick Kennedy PACK 14
18 Aug Oliver Brewer INSP 32 1
18 Aug Harinder Singh ASSY 22 1
18 Aug Dion Field WELD 54 1 1
18 Aug Harinder Singh DRILL 20 1
Ramps built
One serial per ramp, with the batch it came from and who signed it off.
SerialBuiltCapacityLengthBatchWelderInspectedStatus
HY-26-41236 6 Aug 900kg 3.0m VUA-24141 Dion Field Oliver Brewer In stock
HY-26-41237 2 Jul 900kg 3.0m VUA-24189 Dion Field Oliver Brewer In stock