Contract value
$880
no variations
Quoted cost
$695
$500 material · 2.0h
Actual so far
$906
$614 material · 3.0h
Margin
-2.9%
on actual cost
Invoiced
$880
$1,136 received
Production
What is being built against this job.
| Order | Model | Qty | Stage | Hours | Material | Due |
|---|---|---|---|---|---|---|
| PO-26-0114 | ATVR21 ATV Aluminium Ramps | 2/2 | Complete | 3.0 / 2.8 | $614 / $500 | 14 Jan |
Variations
Priced and approved separately. The original quotation and specification stay as they were.
None on this job.
Drawings and documents
The workshop only ever sees the current revision.
Nothing filed against this job.
Ramps built on this job
Serial numbers stay against the job and the customer for the life of the ramp.
| Serial | Model | Built | Batch | Welder | Status | Warranty to |
|---|---|---|---|---|---|---|
| HY-26-41286 | ATVR21 | 20 Jul | VUA-24332 | Nelson De Villa | In service | 14 Aug |
| HY-26-41287 | ATVR21 | 10 Aug | VUA-24284 | Dion Field | In service | 14 Aug |
| HY-26-41288 | ATVR21 | 3 Aug | VUA-24499 | Dion Field | In service | 14 Aug |
| HY-26-41289 | ATVR21 | 27 Jul | VUA-24164 | Dion Field | In service | 14 Aug |
Labour booked
3.0 hours against 2.8 estimated.
| Date | Who | Centre | Order | Minutes | Note |
|---|---|---|---|---|---|
| 19 Aug | Harinder Singh | CUT | PO-26-0114 | 30 | |
| 19 Aug | Harinder Singh | DRILL | PO-26-0114 | 19 | |
| 19 Aug | Nelson De Villa | WELD | PO-26-0114 | 55 | |
| 19 Aug | Oliver Brewer | INSP | PO-26-0114 | 32 | |
| 19 Aug | Nick Kennedy | PACK | PO-26-0114 | 19 | |
| 18 Aug | Harinder Singh | ASSY | PO-26-0114 | 23 |