Contract value
$1,650
no variations
Quoted cost
$957
$593 material · 3.7h
Actual so far
$930
$569 material · 3.7h
Margin
43.7%
on actual cost
Invoiced
$1,650
$1,400 received
The specification
Captured on the enquiry and unchanged since. Variations sit alongside it, not over it.
Toro Groundsmaster 4000-D mower
| All-up weight | 1,450kg |
| Axle / track load | 800kg |
| Track width | 1,620mm |
| Deck height | 760mm |
| Gradient | 33% |
| Attachment | Hook over |
The ramps
1,750kg
rated per pair
2.3m
length
400mm
rung width
L100
profile
ID welding, Anti-slip decking
Production
What is being built against this job.
| Order | Model | Qty | Stage | Hours | Material | Due |
|---|---|---|---|---|---|---|
| PO-26-0112 | L100 210 2500kg Aluminium Ramps at 2.1m | 1/1 | Complete | 3.7 / 2.9 | $569 / $593 | 21 Jun |
Variations
Priced and approved separately. The original quotation and specification stay as they were.
None on this job.
Drawings and documents
The workshop only ever sees the current revision.
Nothing filed against this job.
Ramps built on this job
Serial numbers stay against the job and the customer for the life of the ramp.
| Serial | Model | Built | Batch | Welder | Status | Warranty to |
|---|---|---|---|---|---|---|
| HY-26-41282 | L100 210 | 13 Aug | VUA-24733 | Nelson De Villa | In service | 10 Aug |
| HY-26-41283 | L100 210 | 6 Aug | VUA-24305 | Dion Field | In service | 10 Aug |
Labour booked
3.7 hours against 2.9 estimated.
| Date | Who | Centre | Order | Minutes | Note |
|---|---|---|---|---|---|
| 19 Aug | Harinder Singh | DRILL | PO-26-0112 | 23 | |
| 19 Aug | Dion Field | WELD | PO-26-0112 | 68 | |
| 19 Aug | Harinder Singh | ASSY | PO-26-0112 | 30 | |
| 19 Aug | Oliver Brewer | INSP | PO-26-0112 | 40 | |
| 19 Aug | Nick Kennedy | PACK | PO-26-0112 | 25 | |
| 18 Aug | Harinder Singh | CUT | PO-26-0112 | 35 |