Contract value
$4,748
no variations
Quoted cost
$2,548
$1,834 material · 7.3h
Actual so far
$1,777
$1,303 material · 4.8h
Margin
46.3%
on the quote
Invoiced
$0
$0 received
Production
What is being built against this job.
| Order | Model | Qty | Stage | Hours | Material | Due |
|---|---|---|---|---|---|---|
| PO-26-0435 | L75 240 1200kg Aluminium Ramps at 2.4m | 1/3 | Welding | 3.8 / 7.3 | $966 / $1,393 | 20 Aug |
| PO-26-0436 | L70 270 750kg Aluminium Ramps at 2.7m | 0/1 | Assembly | 1.0 / 1.9 | $337 / $365 | 20 Aug |
Variations
Priced and approved separately. The original quotation and specification stay as they were.
None on this job.
Drawings and documents
The workshop only ever sees the current revision.
Nothing filed against this job.
Labour booked
4.8 hours against 9.2 estimated.
| Date | Who | Centre | Order | Minutes | Note |
|---|---|---|---|---|---|
| 19 Aug | Harinder Singh | CUT | PO-26-0435 | 69 | |
| 19 Aug | Nelson De Villa | WELD | PO-26-0435 | 61 | |
| 19 Aug | Harinder Singh | DRILL | PO-26-0436 | 16 | |
| 19 Aug | Dion Field | WELD | PO-26-0436 | 31 | |
| 19 Aug | Harinder Singh | ASSY | PO-26-0436 | 7 | |
| 18 Aug | Harinder Singh | DRILL | PO-26-0435 | 48 | |
| 18 Aug | Harinder Singh | CUT | PO-26-0436 | 18 |