Hyway Hyway
Hyway Hyway
Production order PO-26-0118 Demo 1 × 200/360 · Complete
Xero connected · synced 9:14am 19 Aug 2026
← The floor Complete
Pairs
1/1
none scrapped
Hours
4.7
against 4.4h estimated
Material issued
$0
of $0 planned
Scrap off the saw
0.00kg
0 cut plans run
Off the remnant rack
0.0m
metal not bought new
Routing
Standard minutes against booked, work centre by work centre.
SeqWork centreWhat happensWhoStatusStdBookedVariance
1 CUT Cutting — 4 rails at 3600mm, 26 rungs at 524mm Harinder Singh Done 41 min 44 +7%
2 DRILL Drilling — Rail jig, headplate and pin holes Harinder Singh Done 27 min 29 +7%
3 WELD Welding — 52 rung joins, 2 headplates Nelson De Villa Done 93 min 99 +6%
4 ASSY Assembly — Nose, lugs, pins, ID plate Harinder Singh Done 34 min 36 +6%
5 INSP Inspection — Proof load and dimensional check Oliver Brewer Done 40 min 43 +8%
6 PACK Packing — Bearers, strap, wrap, label Nick Kennedy Done 30 min 32 +7%
Cutting and nesting
What has to be cut to length, and how it was nested onto bar and remnant.
Nothing on this order is cut to length.
Material
Required against issued, priced at what the buyer last paid.
CodeMaterialBinRequiredIssuedOn handCost
Planned material$0.00
Labour booked
4.7 hours off the floor against this order.
DateWhoWork centreMinutesDoneScrapNote
19 Aug Harinder Singh ASSY 36 1
19 Aug Harinder Singh CUT 44 1
18 Aug Nick Kennedy PACK 32 1
18 Aug Oliver Brewer INSP 43 1
18 Aug Nelson De Villa WELD 99 1 Rung join reworked — porosity on the second pass
18 Aug Harinder Singh DRILL 29 1
Ramps built
One serial per ramp, with the batch it came from and who signed it off.
SerialBuiltCapacityLengthBatchWelderInspectedStatus
HY-26-41302 14 Aug 7,500kg 3.6m VUA-24923 Dion Field Oliver Brewer In service
HY-26-41303 25 Jun 7,500kg 3.6m VUA-24844 Nelson De Villa Oliver Brewer In service