Production order PO-26-0113 Demo 1 × ATVR21 · Complete
Xero connected · synced 9:14am 19 Aug 2026
← The floor Complete
Pairs
1/1
1 scrapped
Hours
2.1
against 1.9h estimated
Material issued
$0
of $0 planned
Scrap off the saw
0.00kg
0 cut plans run
Off the remnant rack
0.0m
metal not bought new
Routing
Standard minutes against booked, work centre by work centre.
SeqWork centreWhat happensWhoStatusStdBookedVariance
1 CUT Cutting — 4 rails at 2100mm, 16 rungs at 264mm Harinder Singh Done 20 min 23 +15%
2 DRILL Drilling — Rail jig, headplate and pin holes Harinder Singh Done 13 min 15 +15%
3 WELD Welding — 32 rung joins, 2 headplates Nelson De Villa Done 33 min 38 +15%
4 ASSY Assembly — Nose, lugs, pins, ID plate Harinder Singh Done 14 min 16 +14%
5 INSP Inspection — Dimensional check and weld inspection Oliver Brewer Done 20 min 23 +15%
6 PACK Packing — Bearers, strap, wrap, label Nick Kennedy Done 11 min 13 +18%
Cutting and nesting
What has to be cut to length, and how it was nested onto bar and remnant.
Nothing on this order is cut to length.
Material
Required against issued, priced at what the buyer last paid.
CodeMaterialBinRequiredIssuedOn handCost
Planned material$0.00
Labour booked
2.1 hours off the floor against this order.
DateWhoWork centreMinutesDoneScrapNote
19 Aug Nick Kennedy PACK 13 1
19 Aug Harinder Singh DRILL 15 1
19 Aug Harinder Singh CUT 23 1
18 Aug Oliver Brewer INSP 23 1
18 Aug Harinder Singh ASSY 16 1
18 Aug Nelson De Villa WELD 38 1
Ramps built
One serial per ramp, with the batch it came from and who signed it off.
SerialBuiltCapacityLengthBatchWelderInspectedStatus
HY-26-41284 26 Jun 500kg 2.1m VUA-24830 Nelson De Villa Oliver Brewer In service