Production order PO-26-0107 Demo 1 × 200/360 · Complete
Xero connected · synced 9:14am 19 Aug 2026
← The floor Complete
Pairs
1/1
none scrapped
Hours
5.8
against 4.4h estimated
Material issued
$0
of $0 planned
Scrap off the saw
0.00kg
0 cut plans run
Off the remnant rack
0.0m
metal not bought new
Routing
Standard minutes against booked, work centre by work centre.
SeqWork centreWhat happensWhoStatusStdBookedVariance
1 CUT Cutting — 4 rails at 3600mm, 26 rungs at 524mm Harinder Singh Done 41 min 54 +32%
2 DRILL Drilling — Rail jig, headplate and pin holes Harinder Singh Done 27 min 36 +33%
3 WELD Welding — 52 rung joins, 2 headplates Dion Field Done 93 min 123 +32%
4 ASSY Assembly — Nose, lugs, pins, ID plate Harinder Singh Done 34 min 45 +32%
5 INSP Inspection — Proof load and dimensional check Oliver Brewer Done 40 min 53 +33%
6 PACK Packing — Bearers, strap, wrap, label Nick Kennedy Done 30 min 40 +33%
Cutting and nesting
What has to be cut to length, and how it was nested onto bar and remnant.
Nothing on this order is cut to length.
Material
Required against issued, priced at what the buyer last paid.
CodeMaterialBinRequiredIssuedOn handCost
Planned material$0.00
Labour booked
5.9 hours off the floor against this order.
DateWhoWork centreMinutesDoneScrapNote
19 Aug Harinder Singh ASSY 45 1
19 Aug Dion Field WELD 123 1
18 Aug Nick Kennedy PACK 40 1
18 Aug Oliver Brewer INSP 53 1
18 Aug Harinder Singh DRILL 36 1
18 Aug Harinder Singh CUT 54 1
Ramps built
One serial per ramp, with the batch it came from and who signed it off.
SerialBuiltCapacityLengthBatchWelderInspectedStatus
HY-26-41262 25 Jun 7,500kg 3.6m VUA-24539 Dion Field Oliver Brewer In service
HY-26-41263 7 Jul 7,500kg 3.6m VUA-24538 Dion Field Oliver Brewer In service