Production is held on this job
Nothing goes to the floor until the deposit has been received and the customer has approved the drawing. PO-26-0413 is waiting.
Deposit
$0 of $1,695
Drawing
HD-0148 Rev C
Approved
Contract value
$3,390
no variations
Quoted cost
$1,965
$1,218 material · 7.6h
Actual so far
$0
$0 material · 0.0h
Margin
42.0%
on the quote
Invoiced
$0
$0 received
The specification
Captured on the enquiry and unchanged since. Variations sit alongside it, not over it.
Merlo P27.6 telehandler
| All-up weight | 5,800kg |
| Axle / track load | 3,200kg |
| Track width | 1,980mm |
| Deck height | 1,040mm |
| Gradient | 30% |
| Attachment | Lugs |
The ramps
6,750kg
rated per pair
3.5m
length
500mm
rung width
175
profile
Production
What is being built against this job.
| Order | Model | Qty | Stage | Hours | Material | Due |
|---|---|---|---|---|---|---|
| PO-26-0413 Deposit outstanding | 175/360 6000kg Aluminium Ramps at 3.6m | 0/1 | Planned | 0.0 / 4.4 | $0 / $1,473 | 21 Aug |
Variations
Priced and approved separately. The original quotation and specification stay as they were.
None on this job.
Drawings and documents
The workshop only ever sees the current revision.
| Document | Kind | Rev | Status | Filed by | When |
|---|---|---|---|---|---|
| Signed drawing approval | Approval | A | Current | Leigh Sharland | 11 Aug, 14:40 |
| HD-0148 Rev C — general arrangement | Drawing | C | Current | Oliver Brewer | 5 Aug, 10:20 |
| HD-0148 Rev A — general arrangement | Drawing | A | Superseded | Oliver Brewer | 15 Jul, 08:20 |
| HD-0148 Rev B — general arrangement | Drawing | B | Superseded | Oliver Brewer | 12 Jul, 09:20 |
| Safe use and inspection booklet | Safety | 2026-1 | Current | Leigh Sharland | 4 Aug, 10:00 |
| Machine specification sheet — customer supplied | Specification | A | Current | Nick Harrison | 18 Jul, 11:05 |