Contract value
$4,297
no variations
Quoted cost
$2,487
$1,542 material · 9.6h
Actual so far
$1,332
$1,105 material · 2.3h
Margin
42.1%
on the quote
Invoiced
$1,868
$2,149 received
The specification
Captured on the enquiry and unchanged since. Variations sit alongside it, not over it.
Case 580SN backhoe
| All-up weight | 7,300kg |
| Axle / track load | 4,000kg |
| Track width | 2,240mm |
| Deck height | 1,120mm |
| Gradient | 30% |
| Attachment | Lugs |
The ramps
8,500kg
rated per pair
3.7m
length
600mm
rung width
200
profile
Extra pins
Production
What is being built against this job.
| Order | Model | Qty | Stage | Hours | Material | Due |
|---|---|---|---|---|---|---|
| PO-26-0402 | 200/360 7500kg Aluminium Ramps at 3.6m | 0/1 | Welding | 2.3 / 4.4 | $1,105 / $1,627 | 10 Sep |
Variations
Priced and approved separately. The original quotation and specification stay as they were.
None on this job.
Drawings and documents
The workshop only ever sees the current revision.
| Document | Kind | Rev | Status | Filed by | When |
|---|---|---|---|---|---|
| Signed drawing approval | Approval | A | Current | Leigh Sharland | 2 Aug, 14:40 |
| HD-0133 Rev C — general arrangement | Drawing | C | Current | Oliver Brewer | 11 Aug, 10:20 |
| HD-0133 Rev B — general arrangement | Drawing | B | Superseded | Oliver Brewer | 10 Aug, 09:20 |
| HD-0133 Rev A — general arrangement | Drawing | A | Superseded | Oliver Brewer | 10 Jul, 08:20 |
| Safe use and inspection booklet | Safety | 2026-1 | Current | Leigh Sharland | 17 Aug, 10:00 |
| Machine specification sheet — customer supplied | Specification | A | Current | Nick Harrison | 7 Jul, 11:05 |
Labour booked
2.3 hours against 4.4 estimated.
| Date | Who | Centre | Order | Minutes | Note |
|---|---|---|---|---|---|
| 19 Aug | Harinder Singh | CUT | PO-26-0402 | 41 | |
| 19 Aug | Nelson De Villa | WELD | PO-26-0402 | 63 | Rung join reworked — porosity on the second pass |
| 18 Aug | Harinder Singh | DRILL | PO-26-0402 | 31 |