Production order PO-26-0121 Demo 1 × 150/330 · Complete
Xero connected · synced 9:14am 19 Aug 2026
← The floor Complete
Pairs
1/1
none scrapped
Hours
4.7
against 4.2h estimated
Material issued
$0
of $0 planned
Scrap off the saw
0.00kg
0 cut plans run
Off the remnant rack
0.0m
metal not bought new
Routing
Standard minutes against booked, work centre by work centre.
SeqWork centreWhat happensWhoStatusStdBookedVariance
1 CUT Cutting — 4 rails at 3300mm, 22 rungs at 424mm Harinder Singh Done 39 min 45 +15%
2 DRILL Drilling — Rail jig, headplate and pin holes Harinder Singh Done 25 min 29 +16%
3 WELD Welding — 44 rung joins, 2 headplates Dion Field Done 84 min 96 +14%
4 ASSY Assembly — Nose, lugs, pins, ID plate Harinder Singh Done 32 min 37 +16%
5 INSP Inspection — Proof load and dimensional check Oliver Brewer Done 40 min 46 +15%
6 PACK Packing — Bearers, strap, wrap, label Nick Kennedy Done 29 min 33 +14%
Cutting and nesting
What has to be cut to length, and how it was nested onto bar and remnant.
Nothing on this order is cut to length.
Material
Required against issued, priced at what the buyer last paid.
CodeMaterialBinRequiredIssuedOn handCost
Planned material$0.00
Labour booked
4.8 hours off the floor against this order.
DateWhoWork centreMinutesDoneScrapNote
19 Aug Nick Kennedy PACK 33 1
19 Aug Oliver Brewer INSP 46 1
19 Aug Harinder Singh ASSY 37 1
18 Aug Dion Field WELD 96 1
18 Aug Harinder Singh DRILL 29 1
18 Aug Harinder Singh CUT 45 1
Ramps built
One serial per ramp, with the batch it came from and who signed it off.
SerialBuiltCapacityLengthBatchWelderInspectedStatus
HY-26-41312 5 Aug 4,500kg 3.3m VUA-24328 Nelson De Villa Oliver Brewer In service
HY-26-41313 10 Aug 4,500kg 3.3m VUA-24032 Nelson De Villa Oliver Brewer In service