Contract value
$4,495
no variations
Quoted cost
$2,608
$1,617 material · 10.1h
Actual so far
$2,179
$1,659 material · 5.3h
Margin
51.5%
on actual cost
Invoiced
$4,495
$5,232 received
The specification
Captured on the enquiry and unchanged since. Variations sit alongside it, not over it.
JCB 3CX backhoe
| All-up weight | 8,100kg |
| Axle / track load | 4,400kg |
| Track width | 2,290mm |
| Deck height | 1,150mm |
| Gradient | 28% |
| Attachment | Lugs |
The ramps
9,500kg
rated per pair
4.1m
length
600mm
rung width
200
profile
Production
What is being built against this job.
| Order | Model | Qty | Stage | Hours | Material | Due |
|---|---|---|---|---|---|---|
| PO-26-0103 | 200/360 7500kg Aluminium Ramps at 3.6m | 1/1 | Complete | 5.3 / 4.4 | $1,659 / $1,617 | 29 Mar |
Variations
Priced and approved separately. The original quotation and specification stay as they were.
None on this job.
Drawings and documents
The workshop only ever sees the current revision.
Nothing filed against this job.
Ramps built on this job
Serial numbers stay against the job and the customer for the life of the ramp.
| Serial | Model | Built | Batch | Welder | Status | Warranty to |
|---|---|---|---|---|---|---|
| HY-26-41254 | 200/360 | 28 Jul | VUA-24872 | Nelson De Villa | In service | 20 Jul |
| HY-26-41255 | 200/360 | 11 Aug | VUA-24677 | Nelson De Villa | In service | 20 Jul |
Labour booked
5.3 hours against 4.4 estimated.
| Date | Who | Centre | Order | Minutes | Note |
|---|---|---|---|---|---|
| 19 Aug | Harinder Singh | CUT | PO-26-0103 | 49 | |
| 19 Aug | Harinder Singh | DRILL | PO-26-0103 | 32 | |
| 18 Aug | Dion Field | WELD | PO-26-0103 | 112 | |
| 18 Aug | Harinder Singh | ASSY | PO-26-0103 | 41 | |
| 18 Aug | Oliver Brewer | INSP | PO-26-0103 | 48 | |
| 18 Aug | Nick Kennedy | PACK | PO-26-0103 | 36 |